1) Operation:
runs OK. No intervention is needed after power outage.
2) FDR-2 and CCRC:
CCRC-2 starts 5/5. FDR-2 starts 6/2-8. BNL will get at least 250TB (disk
and/or tape, RAW, ESD, AOD, etc). Haven't decided how much will
distribute to Tier 2s. Michael suggested 1/3 instead of 100% AODs to
each Tier 2 site.
3) Infrastructure:
5 (out of 7) new thumpers are in service, each provides 32TB usable space.
Two additional gridftp servers are in service though we want to use more
than on network port on each of them. At the moment, we estimated this
will allow 200MByte/s from BNL to SLAC.
4) AOB
SRM is in service and proved to work with DQ2. Believe the last issue
with PandaMover is also solved.
Wei Yang | [log in to unmask] | 650-926-3338(O)
Kim, Peter C. wrote:
> ATLAS SCCS Planning, April 30, 2008
> -------------------------------------------------------
>
> 9:00 AM, SCCS Conf Rm A,
>
> to call in +1 510 665 5437, press 1, 3935#
>
>
> Agenda:
>
> 1. Tier-2 Operations (Panda & pAthena)
>
> 2. FDR-2 Readiness
>
> 3. Tier-2 Infrastructure and Hardware
>
> 4. AOB
>
> =================================
> I can not participate while travelling today.
> Wei would keep the meeting minutes.
>
> FDR-2 update: There has been many problems trying
> to build the ATLAS software release for the FDR-2.
> It was finally built yesterday, 2 weeks late.
> Subsequently FDR-2 is now scheduled for June 2-8.
> The amount of data produced will also be curtailed,
> but the exact amount is not yet decided.
>
>
>
>
>
>
|