[I'll be on a plane so Charlie will run the meeting]

ATLAS SCCS Planning 24May2006
-----------------------------

Present:

Agenda:

1. DQ2 Status/Web Proxy

2. mysql replica Status

3. Trigger Farm Status

4. ATLAS Oracle Server

5. AOB

Action Items:
-------------

060503 Len  Talk to Chuck about Tier-2 meeting

060412 Systems  Provide Oracle service for ATLAS Trigger testing (RT
46089)
       060419 No ticket yet, so nothing done.
       060426 Now have ticket 46089.
       060503 No news.

060224 Stephen	Enquire with ATLAS about certificates for DQ2 machine
       060301 Not heard back from ATLAS folk, Wei pointed out a DoE
	      place to get service certificates.
       060308 No update.
       060315 No update.
       060405 No update.
       060412 No update.
       060419 No update.
       060426 No update.
       060503 Latest revelation about grid proxy issues illustrats
	      this should be solved.

060224 Systems	Provide DQ2 machine (RT 43380)
       060301 In the queue.
       060308 Not done yet.
       060315 Not done yet.
       060405 No update.
       060412 No update.
       060417 Will try to allocation machine today.
       060426 In the queue.
       060503 Power, racl, network and dns done. No OS yet.

060224 Systems	Provide mysql replica (RT 43381)
       060301 In the queue.
       060308 Not done yet.
       060315 Not done yet.
       060405 No update.
       060412 No update.
       060417 Will try to allocation machine today.
       060426 In the queue.
       060503 Power, racl, network and dns done. No OS yet.

060224 Chuck	Will check on web server request for DQ2 machine
       060301 Waiting for web server request information from Stephen.
       060308 Haven't checked yet; haven't received Stephen's request yet.
       060315 Still not sent Chuck information.
       060405 No update.
       060412 No update.
       060419 No update.
       060426 Resubmitted request as it was lost before.
       060503 Not heard anything for about two weeks.

060224 Richard	Discuss ATLAS trigger machines with others in SCCS
       060301 Only limited response from John W was resigned
	      acceptance... need to work on an actual deployment plan as
	      there are real issues to be solved.
       060308 John aware and in plans as much as anything is. New
	      engineer will take over.
       060315 No update.
       060405 No update.
       060412 No update.
       060419 No update.
       060426 No update.
       060503 No update.


--
 /------------------------------------+-------------------------\
|Stephen J. Gowdy, SLAC               | CERN     Office: 32-2-A22|
|http://www.slac.stanford.edu/~gowdy/ | CH-1211 Geneva 23        |
|http://calendar.yahoo.com/gowdy      | Switzerland              |
|EMail: [log in to unmask]       | Tel: +41 22 767 5840     |
 \------------------------------------+-------------------------/