Ok, here is what I'm planning to ask Sun to quote for the
initial Atlas farm:

3 18TB fileservers: V240 + 3 tray 6140 (1 controller + 2 expansion)
64 Compute nodes: X2200M2, 2x2214, 8GB (8x1GB DIMMS), 2x250GB drive

The storage should come to around $152K and the compute nodes
to around $223K.  That comes about $25K short of $400K, which
we can either hold back to fix miscalculations (e.g., too much
storage per server, have to buy more fileservers to spread
the load), or we can buy 5 or 6 more batch nodes.

Any last-minute course corrections before I go ahead with this?

Chuck Boeheim