Hmmm, I was afraid we did not do a good job clarifying this.  Sorry Stephen.

On Wed, 28 Feb 2007 18:23:08 +0100 (CET)  "Stephen J. Gowdy" wrote:

> 2. Tier-2 Hardware
> 
>     Terry now has the order and is processing it. 3 Thumpers and 78
>     X2200 M2s (8GB and a pair of two 50GB drives) was the final order.

                                   two 250GB drives

> 
>     Assuming usual time to get through purchasing it will be three to
>     four weeks before it starts showing up.
> 
>     Then it is a week to install hardware and a week for software
>     install.
> 
>     Power will not be available till the end of May but hope can find
>     5A for one of the Thumpers.