Hmmm, I was afraid we did not do a good job clarifying this. Sorry Stephen. On Wed, 28 Feb 2007 18:23:08 +0100 (CET) "Stephen J. Gowdy" wrote: > 2. Tier-2 Hardware > > Terry now has the order and is processing it. 3 Thumpers and 78 > X2200 M2s (8GB and a pair of two 50GB drives) was the final order. two 250GB drives > > Assuming usual time to get through purchasing it will be three to > four weeks before it starts showing up. > > Then it is a week to install hardware and a week for software > install. > > Power will not be available till the end of May but hope can find > 5A for one of the Thumpers.