Hi Charlie,

>From January 5-12, we had an outage for cooling pipeline upgrade, and we
agreed with SCCS to close batch nodes from midnight, January 3. That is a
period of 9 ~ 10 days. I think that is the ~ 2/3 availability data coming
from.

Regards,
Wei Yang  |  [log in to unmask]  |  650-926-3338(O)

> From: "Young, Charles C." <[log in to unmask]>
> Date: Sun, 15 Feb 2009 06:28:38 -0800
> To: Wei Yang <[log in to unmask]>,
> "[log in to unmask]"
> <[log in to unmask]>
> Subject: RE: January 2009 - Tier-2 Reliability and Availability Report
> 
> Hi Wei,
> 
> I guess Available is normalized to (effectively) 24 hours a day and 365
> days a week, without regard to planned down times, is that right? If we
> factor out the planned outage, what would 64% become? Cheers.
> 
> Charlie
> 
> PS: I am not asking for 3 decimal place accuracy. Just ball park number.
> 
> --
> Charles C. Young
> M.S. 43, Stanford Linear Accelerator Center
> P.O. Box 20450   
> Stanford, CA 94309
> [log in to unmask]
> voice  (650) 926 2669
> fax    (650) 926 2923
> CERN GSM +41 76 487 2069
> 
>> -----Original Message-----
>> From: [log in to unmask]
>> [mailto:[log in to unmask]] On
>> Behalf Of Wei Yang
>> Sent: Thursday, February 12, 2009 7:44 PM
>> To: [log in to unmask]
>> Subject: FW: January 2009 - Tier-2 Reliability and Availability Report
>> 
>> ------ Forwarded Message
>> From: Lcg Office <[log in to unmask]>
>> Date: Thu, 12 Feb 2009 14:47:00 +0100
>> To: "project-wlcg-cb (Members of the WLCG CB)"
>> <[log in to unmask]>
>> Cc: "project-lcg-gdb (LCG - Grid Deployment Board)"
>> <[log in to unmask]>
>> Subject: January 2009 - Tier-2 Reliability and Availability Report
>> 
>> 
>> Dear Collaboration Board Members,
>> 
>> Find below the draft WLCG Reliability and Availability Report
>> for the Tier-2 sites for last month.
>>  
>> https://twiki.cern.ch/twiki/bin/viewfile/LCG/SamMbReports?file
>> name=Tier2_Rel
>> iab_200901.pdf
>>  
>> Please send your comments and corrections to
>> [log in to unmask] before Wednesday 18 February 2009.
>> 
>> The report will then be published on the WLCG web site and
>> reported to the WLCG Overview Board.
>>  
>> Best regards.
>> Alberto Aimar, LCG Office
>> 
>> 
>> 
>> ------ End of Forwarded Message
>> 
>>