ATLAS SCCS Planning Oct 14, 2009
---------------------------------------------------- 
 
  9am, SCCS Conf Rm A, to call in +1 510 665 5437, press 1, 3935#
  Present: Wei, Peter, Booker, Richard, Stefan
 
Agenda:
 
1. Status of WT2 2009 hardware
 
   - With default allocation of 2/3 Storage and 1/3 CPU,
     the following have been purchased ($400k). 
 
      DELL Poweredge R410, 2.8 GHz 8-core, 24G memory
      SUN X4540 Thor, 48 1-TB disks, 2.7GHz quad-core (10 units) 
 
  - All CPUs and disk storage have been delivered to SLAC. 
    Work is ongoing to install them; allocate rack space, power, 
    cooling, etc.  The plan is to have them ready for use before 
    ATLAS data arrives, with a higher priority given to the storage.     
 
2. Tier-2 Production and Operations
 
  - No issues with PANDA operations at SLAC.
    The problem with GRID certificates was traced to westgrid.ca.
    (triumf.ca is fine.). SRM service at LBNL and BNL folks are
    looking into the problem.
 
  - OSG upgrade completed; it requires lots of hands-on work
     by Booker and Wei once a year
 
  - New Frontier farm server has been installed. With 8GB memory
    and 3 Gb internal channel, it functions fine. More units can be 
    added as needed.
 
  - User Analysis Test (UAT) is scheduled for Oct. 22-24.
     (It is now postponed to Oct. 28-30.)
 
3. Status of SLC5/RHEL5 for WT2
 
   - Wei reported that 100 CPUs in WT2 farm have been migrated
      to REHL5-64, after validations by Booker and Wei. No issues 
      with PANDA operations on these machines.
      Migration of the rest is to follow.
 
4. AOB