Okay, I'll update those items.

8.2 means Wired.

On Thu, 13 Jun 2013, Graf, Norman A. wrote:

> Hello Sho,
> I had agreed to take on the tracking items 7.1.1 - 7.1.4
> at the collaboration meeting. They will be done by the
> deadline given.
> I can also complete 4.3.
> I would add 4.4 "add additional dead material, e.g. dipole"
> for which I can also furnish the geometry.
> Item 4.4 is done. We are just waiting on the input map.
>  I am not sure what item 8.2 needs. Is this something other
>  than Wired?
> Norman
>
> ________________________________________
> From: [log in to unmask] [[log in to unmask]] On Behalf Of Sho Uemura [[log in to unmask]]
> Sent: Thursday, June 13, 2013 1:34 PM
> To: hps-software
> Subject: draft of software schedule
>
> Here's a first hack at a schedule. It's very rough, but it'll serve as a
> starting point.
>
> Software subgroups should make sure I haven't missed any tasks.
>
>
>
> The current milestones:
>
> Sim production starts September 20.
>
> We are ready to reconstruct data November 29.
>
> We are ready to run February 7 (but there will be tasks added that will
> definitely push this back; see below).
>
>
>
> Tasks, schedule:
> http://www.slac.stanford.edu/~meeg/HPS_software_schedule.png
>
> People:
> http://www.slac.stanford.edu/~meeg/HPS_software_resources.png
>
> Notes on how this is set up:
>
> * Software people have other obligations, so only some fraction of their
> time is going to be spent on software. I'm representing this using the
> "Base Calendar" column. Tell me if you think I've overrepresented your
> availability.
>
> * Task durations are estimates based on 100% time, so a task with 1 week
> duration assigned to someone with 50% time will take 2 weeks on the
> schedule.
>
> * ECal people (Raphael, Andrea, possible grad students/postdocs) are
> lumped together as a single "person" in lieu of actually assigning tasks.
>
> * Analysis tasks aren't listed yet, but should be.
>
> * Some tasks with external dependencies (integration with DAQ, testing
> monitoring at JLab, etc.) aren't listed yet, but should be.
>
> Every task is assigned to someone. If I've assigned tasks to you, you
> should tell me whether the duration is plausible and you're the right
> person to do it.
>
>
> Thanks in advance for feedback.
>
> ########################################################################
> Use REPLY-ALL to reply to list
>
> To unsubscribe from the HPS-SOFTWARE list, click the following link:
> https://listserv.slac.stanford.edu/cgi-bin/wa?SUBED1=HPS-SOFTWARE&A=1
>

########################################################################
Use REPLY-ALL to reply to list

To unsubscribe from the HPS-SOFTWARE list, click the following link:
https://listserv.slac.stanford.edu/cgi-bin/wa?SUBED1=HPS-SOFTWARE&A=1