Dear all,

The final T2 reliability & availability report for November is here:


Please also check the new VO-based reports for November here, which include all re-computation requests received.

Kind regards,
Cath

-----------------------------------------------
WLCG Office
IT Dept - CERN
CH-1211 Genève, Switzerland
www.cern.ch/wlcg

From: WLCG Office
Sent: 05 December 2013 09:28
To: project-wlcg-cb (Members of the WLCG CB)
Cc: project-lcg-gdb (LCG - Grid Deployment Board); sam-support (SAM support); [log in to unmask]; [log in to unmask]
Subject: T2 Reliability & Availability - November 2013

Dear all,

The draft T2 reliability & availability report for November is now available at:


Please verify your data and send comments to WLCG Office by 15 December.

All requests for recomputation must be sent via GGUS within 10 calendar days of this e-mail being sent - further details here.

Reminder: please check the new VO-based Availability Reports - November reports are here.

Kind regards,
Cath


-----------------------------------------------
WLCG Office
IT Dept - CERN
CH-1211 Genève, Switzerland
www.cern.ch/wlcg



Use REPLY-ALL to reply to list

To unsubscribe from the ATLAS-SCCS-PLANNING-L list, click the following link:
https://listserv.slac.stanford.edu/cgi-bin/wa?SUBED1=ATLAS-SCCS-PLANNING-L&A=1