Hello All,
I believe we are very close to being ready for the pass7 reconstruction. All of the issues listed on our checklist at
have been addressed and although tpass7d did identify one new source of error (the "BorderedBandMatrix decomposeBand not positive definite"
exception) I think we could live with that for now.
Jeremy is standing by to make a software release.
So I think we have a few decisions to make.
First, should we proceed with the software release? My opinion is to go ahead and do so. It tags what we have working now and if we wish to start the full production next week it will be available.
If we identify new issues during the testing of tpass7d we can make a new release during the week of November 27 (since both Jeremy and I will be on vacation next week).
Next is when to proceed with the full pass7 reconstruction. Here I am not so sure. I would like to give people a chance to analyze the tpass7d output and sign off on the results. I don't want to rush
this and seeing how it is already Friday afternoon we should give people at least a few days next week. Unfortunately, several of us (me included) will be on vacation next week, so the final decision on whether to start the pass next week will have to be taken
by others.
Please let me know what you think. Unless I hear otherwise I will ask Jeremy to start the software release.
Norman