I won't be able to make it to today's meeting. There is no news on my
action items.
Steffen
On Wed, 9 Aug 2006, Stephen J. Gowdy wrote:
> ATLAS SCCS Planning 09Aug2006
> -----------------------------
>
> SCCS Conf Rm A, to call in +1 510 665 5437, press 1, 3935#
>
> Present:
>
> Agenda:
>
> 1. DQ2 Status/Web Proxy
>
> 2. Trigger Farm Status
>
> 3. ATLAS Oracle Server
>
> 4. Slots for ATLAS Production jobs and other batch related stuff
>
> 5. AOB
>
> Action Items:
> -------------
>
> 060802 Stephen Email Su Dong about Tier2 Workshop
> 060809 Done.
>
> 060802 Stephen Find out about failing ATLAS jobs at SLAC
>
> 060726 Randy Talk to Richard about DQ2 Workshop
> 060802 Wei is well along on planning to going, but BNL has some
> trouble giving access. Normal process takes 90 days but
> hope to be able to do something faster by the 10th
> September.
>
> 060726 Stephen Find out about maximum memory and local storage per job
> 060802 No news yet.
>
> 060412 Systems Provide Oracle service for ATLAS Trigger testing (RT
> 46089)
> 060419 No ticket yet, so nothing done.
> 060426 Now have ticket 46089.
> 060503 No news.
> 060524 Steffen has provided configuration information. Now in
> Chuck's
> hands.
> 060628 Randy will ask Chuck about status.
> 060726 First on list for V240 but not sure when it will
> happen. Will put a T3a on it.
> 060802 John checking for rack space.
>
> 060224 Chuck Will check on web server request for DQ2 machine
> 060301 Waiting for web server request information from Stephen.
> 060308 Haven't checked yet; haven't received Stephen's request yet.
> 060315 Still not sent Chuck information.
> 060405 No update.
> 060412 No update.
> 060419 No update.
> 060426 Resubmitted request as it was lost before.
> 060503 Not heard anything for about two weeks.
> 060524 Stephen need to update ticket, moving from yakut to DQ2
> machine.
> 060628 Request updated now running on atl-dq2, waiting for scan.
> 060726 Meeting on Monday about this.
> 060802 Requesting new user to run services, blocked offsite web
> access, Need to explore MySQL security.
>
> 060224 Richard Discuss ATLAS trigger machines with others in SCCS
> 060301 Only limited response from John W was resigned
> acceptance... need to work on an actual deployment plan as
> there are real issues to be solved.
> 060308 John aware and in plans as much as anything is. New
> engineer will take over.
> 060315 No update.
> 060405 No update.
> 060412 No update.
> 060419 No update.
> 060426 No update.
> 060503 No update.
> 060524 RT 45823. Engineer looking at power availability. On track
> for
> August.
> 060628 Understand schedule, Randy will make sure John is aware.
> 060726 Need to nail down when power will be available. Steffen
> things he can make it happen with existing equipment.
> 060802 Looks like this will fit in SCCS. Can reuse rack,
> switches and fibres.
> k
>
-------------------------------------------------------------------------
- Steffen Luitz - e-mail: [log in to unmask] -
- SLAC Mail Stop 34 - 2575 Sand Hill Rd - Menlo Park, CA 94025 - U.S.A. -
- phone +1 650 926 2822 - cell phone +1 650 796 2266 -
-------------------------------------------------------------------------
|