Dear Colleagues,
In July of this year the Department of Energy conducted
an assessment of the Run II luminosity plan at the
Fermilab Tevatron. The full report is now available
online at:
http://doe-hep.hep.net/RunII_Luminosity_Review_Report.pdf
Appendix D contains the following table:
Integrated Luminosity ( fb^(-1) )
Design Projection Base Projection
per year Accumulated per year Accumulated
FY03 0.22 0.30 0.20 0.28
FY04 0.38 0.68 0.31 0.59
FY05 0.67 1.36 0.39 0.98
FY06 0.89 2.24 0.50 1.48
FY07 1.53 3.78 0.63 2.11
FY08 2.37 6.15 1.14 3.25
FY09 2.42 8.57 1.16 4.41
Norman Graf
|