Hmmm, I was afraid we did not do a good job clarifying this. Sorry Stephen.
On Wed, 28 Feb 2007 18:23:08 +0100 (CET) "Stephen J. Gowdy" wrote:
> 2. Tier-2 Hardware
>
> Terry now has the order and is processing it. 3 Thumpers and 78
> X2200 M2s (8GB and a pair of two 50GB drives) was the final order.
two 250GB drives
>
> Assuming usual time to get through purchasing it will be three to
> four weeks before it starts showing up.
>
> Then it is a week to install hardware and a week for software
> install.
>
> Power will not be available till the end of May but hope can find
> 5A for one of the Thumpers.
|